Project Name: Phase II Active Project of Qingdao Mobile IDC Center
Project Profile:
The construction of China Mobile (Qingdao, Shandong) Cloud Data Center Project officially started in December 2015. The project is located in Hongdao New District and covers an area of over 150,000 square meters, with an overall construction period of 5 years and an investment expected to exceed 3 billion. After completion, 15,000 standard frames can be installed, which will become the largest cloud data center on the eastern coast.
Capacity: LSVG 3200A
Area: Shandong
Control objects: UPS, DC power supply